Free PRINCE2 Agile Foundation exam sample questions
Below we provide 10 free sample PRINCE2 Agile Foundation exam questions to give you a flavour of what you must learn to prepare to sit your PRINCE2 Agile Foundation exam. The answers are given at the bottom.If you want more free exam questions, we have developed 2 complete PRINCE2 Agile Foundation practice exams which form part of our
PRINCE2 Agile Foundation online course.
Question 1
Which of the following agile frameworks is considered suitable for use with PRINCE2 Agile?a) DevOpsb) DSDMc) XPd) Scrum
Question 2
Which is described as list of new features for a product that can be defined in terms of releases, sprints and products?a) Backlogb) Product descriptionc) User storyd) Project Brief
Question 3
Which does NOT describe PRINCE2 Agile according to the eight guidance points?a) PRINCE2 allows for any style of working including environments with high levels of uncertaintyb) PRINCE2 Agile does not assume an IT contextc) A PRINCE2 Agile project that does not use Scrum cannot be considered agiled) Nothing about PRINCE2 should be removed from PRINCE2 Agile project
Question 4
Which of the following statements about fixing and flexing tolerances is INCORRECT?a) Zero tolerance on extra time on all levels of planb) Zero tolerance on benefits defined as “minimum viability” in the business casec) Zero tolerance on quality criteria that are desirable but not essentiald) Zero tolerance on products that are essential
Question 5
Why does PRINCE2 Agile recommend that we ‘protect the level of quality’?a) To avoid inadequate testing as deadlines approachb) To recognize that the customer’s understanding of requirements will evolvec) To give confidence that deadlines can be metd) To avoid the slowing of production as new members are brought up to speed
Question 6
Why does PRINCE2 Agile recommend that we ‘keep teams stable?a) To give confidence to the customer that a usable product will be delivered on a specific dayb) To avoid reduced efficiency as new members are brought up to speedc) To enable fewer high-quality products rather than many of poor qualityd) To ensure that the customer receives the minimum set of products needed to achieve the benefits
Question 7
How does PRINCE2 Agile recommend that the business case management product be tailored?a) The Minimum Viable Product (MVP) should be stated in the business caseb) The business case needs to be written to allow for flexibility on the project timescales and costsc) The benefits in the business case should be fixed and never flexedd) The supplier should be responsible for delivering the benefits
Question 8
Which two statements about the project manager are CORRECT?
- Manages the delivery team
- May be more than one
- Responsible for the day-to-day management of the project
- May be combined with the team manager role in smaller projects
a) 1 and 2b) 2 and 3c) 3 and 4d) 1 and 4
Question 9
Which two statements about ‘the Agilometer’ focus area are CORRECT?
- A decreasing slider score over time shows that the environment is becoming more agile
- A decreasing slider score over time shows that the environment is becoming less agile
- Each slider is independent of the other meaning average agility scores should not be taken
- Each slider is related to the others meaning average agility scores should be taken
a) 1 and 2b) 2 and 3c) 3 and 4d) 1 and 4
Question 10
Which is used to enable all involved in work to ‘pull’ information about targets, progress, issues and risks?a) Burn chartb) Kanban boardc) Information radiatord) Scrum artifact