Sample Exam One

1. Which is one of the six aspects of project performance that need to be managed?

a) 
Scope

b) 
Performance

c) 
Reliability

d) 
Ease of use


2. The purpose of what theme is to establish mechanisms to monitor and compare actual achievements against those planned?

a) 
Quality

b) 
Business Case

c) 
Progress

d) 
Change


3. Which activity within the Controlling a Stage process supports the learn from experience principle?

a) 
Authorize a Work Package

b) 
Review the stage status

c) 
Take corrective action

d) 
Escalate issues and risks


4. What theme provides information on what is required, how it will be achieved and by whom?

a) 
Business Case

b) 
Plans

c) 
Quality

d) 
Organization


5. What process is triggered by the Project Manager's request to initiate a project?

a) 
Initiating a Project

b) 
Managing a Stage Boundary

c) 
Directing a Project

d) 
Starting up a Project


6. Identify the missing words in the following sentence.

A purpose of the Managing a Stage Boundary process is to provide the Project Board with sufficient information so that it can approve the [ ? ] for the next stage.

a) 
Project Brief

b) 
Exception Report

c) 
Stage Plan

d) 
Work Packages


7. Which is an objective of the Closing a Project process?

a) 
Ensure that all benefits have been achieved

b) 
Capture the customer's quality expectations

c) 
Check that all the project's products have been accepted by the users

d) 
Prepare for the final stage of the project


8. What role is responsible for documenting the customer's quality expectations?

a) 
Executive

b) 
Senior User

c) 
Senior Supplier

d) 
Project Manager